WITH the Wismar/Mackenzie Bridge on track to become fully operational by June, construction is progressing steadily, with works now 95.4 per cent complete. According to an update from the Ministry of Public Works on Tuesday, 95 per cent of the concrete has been placed on the 220-metre-long precast structure. Additionally, 60 per cent of the […]